Accueil » Projets » Evaluation and Impact Assessment of the Slum and Shantytown Clearance Support Program
PARHIB

Evaluation and Impact Assessment of the Slum and Shantytown Clearance Support Program

Study

Start date End date Budget Funding
01/11/2009 30/09/2012 300000 € Al Omrane Holding

Partners

South partner(s) : Consultancy firm AREA

Project

  • Defining conformity indicators and technical, social, urban and environmental progress indicators for the operations;
  • Conducting the conformity study;
  • Conducting three progress analysis and producing the related reports in April 2010, December 2010 and December 2011;
  • Defining the methodology and tools for the Social and Economic Impact Assessment;
  • Conducting a qualitative study to assess social, economic, urban and environmental impacts and two quantitative surveys of approximately 1,000 households each 18 months apart (in June 2010 and December 2011);
  • Writing two Social and Economic Impact Assessment reports;
  • Writing a final report;
  • Conducting the interviews and complementary field investigations for the final evaluation of the PARHIB and writing the report;

Editing the final report into a publishable version.

Back